DIGGIN DOWNTOWN UPDATE - 8/22
Date: August 22, 2025
Recent Weeks:
Pavement Removals (Jefferson & Main Intersection)
Underground Utility Installation (Main St)
Subgrade Preparation (East Washington St)
Washington Street West of the Main Street Intersection has opened
Next Week:
Phase 1A Washington Street
Monday 8/25 to Friday 8/29 – Contractor to complete subbase and subdrain installation along East Washington Street.
Phase 1B Main Street
Monday 8/25 to Friday 8/29 – Contractor to continue sanitary service replacements and begin water service replacements along Main Street.
*Please note – Sections of sidewalk along Main Street will be inaccessible while water/sanitary service installation is underway.
Looking Ahead:
East Washington Street will remain closed as paving preparation and installation continues throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.