DIGGIN DOWNTOWN UPDATE - 8/22

Last Updated 8/29/2025Posted in DIGGIN' DOWNTOWN

Date: August 22, 2025

 Recent Weeks:

Pavement Removals (Jefferson & Main Intersection)

Underground Utility Installation (Main St)

Subgrade Preparation (East Washington St)

Washington Street West of the Main Street Intersection has opened                                                      

 Next Week:

Phase 1A Washington Street

Monday 8/25 to Friday 8/29 – Contractor to complete subbase and subdrain installation along East Washington Street.

Phase 1B Main Street

Monday 8/25 to Friday 8/29 – Contractor to continue sanitary service replacements and begin water service replacements along Main Street.

*Please note – Sections of sidewalk along Main Street will be inaccessible while water/sanitary service installation is underway.

Looking Ahead:

East Washington Street will remain closed as paving preparation and installation continues throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.

Diggin Downtown Update 11/21Date: November 21, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Subgrade Compaction, Subbase, Subdrain Ins...
Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...
Diggin Downtown Update - 11/14Date: November 14, 2025 Recent Weeks: Underground Utility Service Installation (W Jefferson St) Subgrade Compaction, Subbase and Subdrai...
DIGGIN DOWNTOWN UPDATE - 11/7Date: November 7, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Permeable Paver installation (Main St) Side...