DIGGIN DOWNTOWN UPDATE - 8/22

Last Updated 8/29/2025Posted in DIGGIN' DOWNTOWN

Date: August 22, 2025

 Recent Weeks:

Pavement Removals (Jefferson & Main Intersection)

Underground Utility Installation (Main St)

Subgrade Preparation (East Washington St)

Washington Street West of the Main Street Intersection has opened                                                      

 Next Week:

Phase 1A Washington Street

Monday 8/25 to Friday 8/29 – Contractor to complete subbase and subdrain installation along East Washington Street.

Phase 1B Main Street

Monday 8/25 to Friday 8/29 – Contractor to continue sanitary service replacements and begin water service replacements along Main Street.

*Please note – Sections of sidewalk along Main Street will be inaccessible while water/sanitary service installation is underway.

Looking Ahead:

East Washington Street will remain closed as paving preparation and installation continues throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.

Halloween Happenings: Frights, Fun, and Festivities Await! Spooky season is creeping in… and Osceola is brewing up a fang-tastic lineup of Halloween fun for all ages! From family trick-or-treatin...
A New Chapter Begins at The Velvet Nook & RoastDowntown Osceola is turning the page on something truly special! On Tuesday, September 30, we gathered to celebrate the ribbon cutting a...
Ribbon Cut & Doors Open at Urban LabelsDowntown Osceola just got a whole lot more stylish! On Tuesday, October 1, we celebrated the grand opening and ribbon cutting of Urban L...
Ribbon Cutting Celebration at Cuban FlavorFriday, September 26, Osceola Chamber Main Street celebrated a ribbon-cutting at Cuban Flavor! Guests enjoyed a festive atmosphere as we...