DIGGIN DOWNTOWN UPDATE - 8/29

Last Updated 8/29/2025Posted in DIGGIN' DOWNTOWN

Date: August 29, 2025


Recent Weeks:

Underground Utility Service Installation (Main St)

Paving Operations (East Washington St)

Fillmore and Washington Intersection has opened

 

Next Week:

(No work to be completed on Monday due to holiday)

Phase 1A Washington Street

Tuesday 9/2 to Friday 9/5 – Contractor to continue paving operations on East Washington Street.

Phase 1B Main Street

Tuesday 9/2 to Friday 9/5 – Contractor to continue water and sanitary service replacement along Main Street.

*Please note – Sections of sidewalk along Main Street will be inaccessible while water/sanitary service installation is underway.


Looking Ahead:

East Washington Street will remain closed as paving preparation and installation continues throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.

DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...
DIGGIN DOWNTOWN UPDATE - 5/16Date: May 22, 2026 Recent Weeks: Permeable Paver Rock Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Next Week: P...
DIGGIN DOWNTOWN UPDATE - 5/15Date: May 15, 2026 Recent Weeks: Permeable Paver Rock Installation (Fillmore St) Subdrain Installation Paving (Fillmore St) Curb and Gut...
Osceola Recognized at 2026 Main Street Iowa Development ... Osceola received statewide recognition at the 2026 Main Street Iowa Development Awards, held May 8 in West Des Moines as Main Street Iow...