DIGGIN DOWNTOWN UPDATE - 8/29

Last Updated 8/29/2025Posted in DIGGIN' DOWNTOWN

Date: August 29, 2025


Recent Weeks:

Underground Utility Service Installation (Main St)

Paving Operations (East Washington St)

Fillmore and Washington Intersection has opened

 

Next Week:

(No work to be completed on Monday due to holiday)

Phase 1A Washington Street

Tuesday 9/2 to Friday 9/5 – Contractor to continue paving operations on East Washington Street.

Phase 1B Main Street

Tuesday 9/2 to Friday 9/5 – Contractor to continue water and sanitary service replacement along Main Street.

*Please note – Sections of sidewalk along Main Street will be inaccessible while water/sanitary service installation is underway.


Looking Ahead:

East Washington Street will remain closed as paving preparation and installation continues throughout the following weeks. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.

DIGGIN DOWNTOWN UPDATE - 8/29Date: August 29, 2025 Recent Weeks: Underground Utility Service Installation (Main St) Paving Operations (East Washington St) Fillmore a...
DIGGIN DOWNTOWN UPDATE - 8/22Date: August 22, 2025 Recent Weeks: Pavement Removals (Jefferson & Main Intersection) Underground Utility Installation (Main St) Subgrad...
DIGGIN DOWNTOWN UPDATE - 8/15Date: August 15, 2025 Recent Weeks: Pavement Removals (Jefferson St & Main St) Underground Utility Installation (Main St) Next Week: Pha...
Osceola Chamber Main Street Lights Up Downtown with New ... Osceola Chamber Main Street has taken another bold step in transforming the heart of downtown into a vibrant, welcoming destination. The...