DIGGIN DOWNTOWN UPDATE - 9/8

Last Updated 9/8/2025Posted in DIGGIN' DOWNTOWN

Date: September 5, 2025

Recent Weeks:

Underground Utility Service Installation (Main St)

Paving Operations (East Washington St)

Pavement Removals (East Jefferson St)

Next Week:

Phase 1A Washington Street

Monday 9/8 to Friday 9/12 – Contractor to continue paving operations on East Washington Street and into intersection of Washington Street and Main Street.

Phase 1B Main Street/Jefferson Street

Monday 9/8 to Friday 9/12:

Main Street: Contractor to make final water main tie in and continue sanitary sewer service installations along Main Street.

East Jefferson: Contractor to continue pavement removals on East Jefferson Street. Alliant will begin replacing gas lines.

*Please note – Sections of sidewalk along Main Street will be inaccessible as sanitary service installation is underway.

Looking Ahead:

Washington Street has been opened for use to the intersection. East Washington Street will remain closed for paving operations. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation.

DIGGIN DOWNTOWN UPDATE - 2/20/26Date: February 20, 2026 Recent Weeks: Water Man Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Install...
DIGGIN DOWNTOWN UPDATE - 2/16/26Date: February 13, 2026 Recent Weeks: Water Main Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Instal...
Ribbon Cutting Celebration: Welcome Vic’s Wash HouseOn February 3, we were proud to welcome Vic’s Wash House to Osceola’s Main Street with a ribbon cutting celebration. It was a great oppo...
Osceola175 - Osceola's Historic DepotAs Osceola celebrates 175 years of community, progress, and connection, our Glimpses of the Past series highlights places and stories th...