DIGGIN DOWNTOWN UPDATE - 9/12

Last Updated 9/22/2025Posted in DIGGIN' DOWNTOWN

Date: September 12, 2025

Recent Weeks:
Underground Utility Service (Main St)
Paving Operations (E Washington St, Washington & Main Street Intersection and Main Street)
East Washington Street is open to the intersection Water line service replacement completed on Main Street
 
Next Week:
Phase 1A Washington Street
Monday 9/15 to Friday 9/19 – Contractor to continue paving operations at intersection of Washington Street and Main Street and sidewalk installation along Main Street.
*Please note – Sections of sidewalk along Main Street will be inaccessible while new sidewalks are being formed and poured.

Phase 1B Main Street/Jefferson Street.
Monday 9/15 to Friday 9/19 – Contractor to continue sanitary sewer service installation then will move to storm sewer installation in the Jefferson/Main intersection. Alliant Energy continues to replace gas line along East Jefferson. Looking Ahead:

Looking Ahead:
Washington and Main Street intersection will remain closed for paving operations. Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation. East Jefferson will remain closed for utility installation.
DIGGIN DOWNTOWN UPDATE - 9/19Date: September 19, 2025 Recent Weeks: Underground Utility Service installation (Main) St/Jefferson St) Paving Operations (Main St/Washi...
September in Osceola: Food, Fun & Fall Vibes!As summer fades and the crispness of fall rolls in, Osceola comes alive with a calendar full of can’t-miss events. This September, the t...
DIGGIN DOWNTOWN UPDATE - 9/12Date: September 12, 2025 Recent Weeks: Underground Utility Service (Main St) Paving Operations (E Washington St, Washington & Main Stree...
DIGGIN DOWNTOWN UPDATE - 9/8Date: September 5, 2025 Recent Weeks: Underground Utility Service Installation (Main St) Paving Operations (East Washington St) Pavement...