DIGGIN DOWNTOWN UPDATE - 9/19

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: September 19, 2025

Recent Weeks:
Underground Utility Service installation (Main) St/Jefferson St)
Paving Operations (Main St/Washington St)
Sidewalk Installation (Main St) Next Week:

Phase 1A Washington Street/Main Street Monday 9/22 to Friday 9/26 – Contractor to work on subgrade prep and paving operations for Main Street road. Contractor to continue paving operations at the Washington/Main Street intersection. Phase 1B Main Street/Jefferson Street.
Monday 9/22 to Friday 9/26 – Contractor to continue utility installation at the intersection of Main Street and Jefferson Street and down East Jefferson Street.

Looking Ahead:
Main Street will remain closed from the Jefferson Street intersection to the Washington Street intersection. East Jefferson will remain closed for utility installation.
DIGGIN DOWNTOWN UPDATE - 2/20/26Date: February 20, 2026 Recent Weeks: Water Man Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Install...
DIGGIN DOWNTOWN UPDATE - 2/16/26Date: February 13, 2026 Recent Weeks: Water Main Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Instal...
Ribbon Cutting Celebration: Welcome Vic’s Wash HouseOn February 3, we were proud to welcome Vic’s Wash House to Osceola’s Main Street with a ribbon cutting celebration. It was a great oppo...
Osceola175 - Osceola's Historic DepotAs Osceola celebrates 175 years of community, progress, and connection, our Glimpses of the Past series highlights places and stories th...