Recent Weeks:
Underground Utility Service installation (Main) St/Jefferson St)
Paving Operations (Main St/Washington St)
Sidewalk Installation (Main St) Next Week:

Phase 1A Washington Street/Main Street Monday 9/22 to Friday 9/26 – Contractor to work on subgrade prep and paving operations for Main Street road. Contractor to continue paving operations at the Washington/Main Street intersection. Phase 1B Main Street/Jefferson Street.
Monday 9/22 to Friday 9/26 – Contractor to continue utility installation at the intersection of Main Street and Jefferson Street and down East Jefferson Street.

Looking Ahead:
Main Street will remain closed from the Jefferson Street intersection to the Washington Street intersection. East Jefferson will remain closed for utility installation.
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/20Date: March 20, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...