DIGGIN' DOWNTOWN UPDATE - 9/26

Last Updated 9/26/2025Posted in DIGGIN' DOWNTOWN

Date: September 26, 2025 

Recent Weeks:
Underground Utility Service Installation (Main St/Jefferson St)
Water Main Installation (E Jefferson St)
Paving Operations (Main St/Washington St)
Light Pole Base Installation (Main Street)

Next Week:
Phase 1A Washington Street/Main Street
Monday 9/29 to Friday 10/3 – Contractor to continue paving operations along Main Street.
Phase 1B Main Street/Jefferson Street.
Monday 9/29 to Friday 10/3 – Contractor to continue utility installation at the intersection of Main Street and Jefferson Street and down East Jefferson Street.

Looking Ahead:
Main Street will remain closed from the Jefferson Street intersection to the Washington Street intersection for paving operations. East Jefferson will remain closed for utility installation.
Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...