Recent Weeks:
Underground Utility Service Installation (Main St/Jefferson St)
Water Main Installation (E Jefferson St)
Paving Operations (Main St/Washington St)
Light Pole Base Installation (Main Street)

Next Week:
Phase 1A Washington Street/Main Street
Monday 9/29 to Friday 10/3 – Contractor to continue paving operations along Main Street.
Phase 1B Main Street/Jefferson Street.
Monday 9/29 to Friday 10/3 – Contractor to continue utility installation at the intersection of Main Street and Jefferson Street and down East Jefferson Street.

Looking Ahead:
Main Street will remain closed from the Jefferson Street intersection to the Washington Street intersection for paving operations. East Jefferson will remain closed for utility installation.
Shop Local This Holiday Season: Osceola Has Something fo... The holiday season is officially here, and as we inch closer to Shop Small Saturday on November 29 , our local businesses are buzzing wi...
DIGGIN DOWNTOWN UPDATE - 11/7Date: November 7, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Permeable Paver installation (Main St) Side...
DIGGIN DOWNTOWN UPDATE - 10/31Date: October 31, 2025 Recent Weeks: Underground Utility Service Installation (Main St/E Jefferson St) Permeable Paver Installation (Mai...
DIGGIN DOWNTOWN UPDATE - 10/24Date: October 24, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Curb and Gutter installation (Main ...