Diggin' Downtown Update - 10/3

Last Updated 10/20/2025Posted in DIGGIN' DOWNTOWN

Date: October 3, 2025

Recent Weeks:

Underground Utility Service Installation (Main St/Jefferson St)

Lighting System Installation (Washington St/Main St)

Paving Operations (Main St)


Next Week:

Phase 1A Washington Street/Main Street

Monday 10/6 to Friday 10/10 

Contractor to install sidewalk ramps at intersection of Washington and Main Street. Contractor will then begin subdrain and curb and gutter installation along Main Street.

Phase 1B Jefferson Street

Monday 10/6 to Friday 10/10 

Contractor to complete storm sewer and sanitary sewer installation along East Jefferson Street.

Looking Ahead:

Main Street will remain closed from Washington intersection through Jefferson intersection for paving operations. East Jefferson to remain closed for utility installation.

DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...
DIGGIN DOWNTOWN 3/6Date: March 6, 2026 Recent Weeks: Water Service Installation (Fillmore St) Sanitary Sewer Service Installation (Fillmore St) Paving Prep...
DIGGIN' DOWNTOWN UPDATE - 2/27Date: February 27, 2026 Recent Weeks: Water Service Installation (Fillmore St) Paving Preparation and Installation (Jefferson St) Next W...