Date: October 24, 2025

 

Recent Weeks:

Underground Utility Service Installation (Main St/Jefferson St)

Curb and Gutter installation (Main St)

Permeable Paver installation (Main St)

Pavement Removals (Jefferson St)

 

Next Week:

Phase 1B Main Street

Monday 10/27 to Friday 10/31 – Contractor to complete permeable paver installation and continue sidewalk installation on Main Street.

Phase 1B Main Street/East Jefferson Street.

Monday 10/27 to Friday 10/31 – Contractor to complete storm sewer installation in the intersection and continue water and sanitary sewer installation along East Jefferson Street

Phase 2A Jefferson Street.

Monday 10/27 to Friday 10/31 Contractor to continue pavement removals along Jefferson Street up to the intersection with Fillmore Street

 

Looking Ahead:

Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation. Jefferson Street between Main Street and Fillmore Street will remain closed for pavement removal.

DIGGIN DOWNTOWN UPDATE - 2/20/26Date: February 20, 2026 Recent Weeks: Water Man Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Install...
DIGGIN DOWNTOWN UPDATE - 2/16/26Date: February 13, 2026 Recent Weeks: Water Main Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Instal...
Ribbon Cutting Celebration: Welcome Vic’s Wash HouseOn February 3, we were proud to welcome Vic’s Wash House to Osceola’s Main Street with a ribbon cutting celebration. It was a great oppo...
Osceola175 - Osceola's Historic DepotAs Osceola celebrates 175 years of community, progress, and connection, our Glimpses of the Past series highlights places and stories th...