DIGGIN DOWNTOWN UPDATE - 10/24

Last Updated 11/10/2025Posted in DIGGIN' DOWNTOWN

Date: October 24, 2025

 

Recent Weeks:

Underground Utility Service Installation (Main St/Jefferson St)

Curb and Gutter installation (Main St)

Permeable Paver installation (Main St)

Pavement Removals (Jefferson St)

 

Next Week:

Phase 1B Main Street

Monday 10/27 to Friday 10/31 – Contractor to complete permeable paver installation and continue sidewalk installation on Main Street.

Phase 1B Main Street/East Jefferson Street.

Monday 10/27 to Friday 10/31 – Contractor to complete storm sewer installation in the intersection and continue water and sanitary sewer installation along East Jefferson Street

Phase 2A Jefferson Street.

Monday 10/27 to Friday 10/31 Contractor to continue pavement removals along Jefferson Street up to the intersection with Fillmore Street

 

Looking Ahead:

Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation. Jefferson Street between Main Street and Fillmore Street will remain closed for pavement removal.

DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/20Date: March 20, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...