DIGGIN DOWNTOWN UPDATE - 10/24

Last Updated 11/10/2025Posted in DIGGIN' DOWNTOWN

Date: October 24, 2025

 

Recent Weeks:

Underground Utility Service Installation (Main St/Jefferson St)

Curb and Gutter installation (Main St)

Permeable Paver installation (Main St)

Pavement Removals (Jefferson St)

 

Next Week:

Phase 1B Main Street

Monday 10/27 to Friday 10/31 – Contractor to complete permeable paver installation and continue sidewalk installation on Main Street.

Phase 1B Main Street/East Jefferson Street.

Monday 10/27 to Friday 10/31 – Contractor to complete storm sewer installation in the intersection and continue water and sanitary sewer installation along East Jefferson Street

Phase 2A Jefferson Street.

Monday 10/27 to Friday 10/31 Contractor to continue pavement removals along Jefferson Street up to the intersection with Fillmore Street

 

Looking Ahead:

Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation. Jefferson Street between Main Street and Fillmore Street will remain closed for pavement removal.

DIGGIN DOWNTOWN UPDATE - 11/7Date: November 7, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Permeable Paver installation (Main St) Side...
DIGGIN DOWNTOWN UPDATE - 10/31Date: October 31, 2025 Recent Weeks: Underground Utility Service Installation (Main St/E Jefferson St) Permeable Paver Installation (Mai...
DIGGIN DOWNTOWN UPDATE - 10/24Date: October 24, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Curb and Gutter installation (Main ...
Diggin Downtown Update - 10/17Date: October 17, 2025 Recent Weeks: Underground Utility Service installation (Main St/Jefferson St) Curb and Gutter installation (Main ...