DIGGIN DOWNTOWN UPDATE - 10/31

Last Updated 11/10/2025Posted in DIGGIN' DOWNTOWN

Date: October 31, 2025


Recent Weeks:

Underground Utility Service Installation (Main St/E Jefferson St)

Permeable Paver Installation (Main St)

Sidewalk Installation (Main Street)

Pavement Removals (West Jefferson St)

 

Next Week:

Phase 1B Main Street

Monday 11/3 to Friday 11/7 – Contractor to complete permeable paver installation and sidewalk installation on Main Street.

Phase 1B Main Street/East Jefferson Street.

Monday 11/3 to Friday 11/7 – Contractor to complete sanitary sewer services and water services along East Jefferson Street. Contractor to begin grading and subgrade preparation in intersection of Main Street and Jefferson Street.

Phase 2A West Jefferson Street.

Thursday 11/6 to Friday 11/7 Contractor to begin water main installation along West Jefferson Street

 

Looking Ahead:

Main Street and the intersection of Main Street and Jefferson Street will remain closed for utility installation and paving operations. Jefferson Street between Main Street and Fillmore Street will remain closed for pavement removal and utility installation.

DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/20Date: March 20, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...