DIGGIN DOWNTOWN UPDATE - 11/7

Last Updated 11/10/2025Posted in DIGGIN' DOWNTOWN

Date: November 7, 2025

Recent Weeks:

Underground Utility Service Installation (Jefferson St)

Permeable Paver installation (Main St)

Sidewalk Installation (Main Street)

Next Week:

Phase 1B Main Street/East Jefferson Street Intersection.

Monday 11/10 to Friday 11/14 – Contractor to begin earthwork, compaction, and subdrain installation.

Phase 2A Jefferson Street.

Monday 11/10 to Friday 11/14 Contractor to continue water main installation.

Looking Ahead:

East Jefferson to the Main Street intersection to remain closed for pavement operations. Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.

DIGGIN DOWNTOWN UPDATE - 2/20/26Date: February 20, 2026 Recent Weeks: Water Man Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Install...
DIGGIN DOWNTOWN UPDATE - 2/16/26Date: February 13, 2026 Recent Weeks: Water Main Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Instal...
Ribbon Cutting Celebration: Welcome Vic’s Wash HouseOn February 3, we were proud to welcome Vic’s Wash House to Osceola’s Main Street with a ribbon cutting celebration. It was a great oppo...
Osceola175 - Osceola's Historic DepotAs Osceola celebrates 175 years of community, progress, and connection, our Glimpses of the Past series highlights places and stories th...