DIGGIN DOWNTOWN UPDATE - 11/7

Last Updated 11/10/2025Posted in DIGGIN' DOWNTOWN

Date: November 7, 2025

Recent Weeks:

Underground Utility Service Installation (Jefferson St)

Permeable Paver installation (Main St)

Sidewalk Installation (Main Street)

Next Week:

Phase 1B Main Street/East Jefferson Street Intersection.

Monday 11/10 to Friday 11/14 – Contractor to begin earthwork, compaction, and subdrain installation.

Phase 2A Jefferson Street.

Monday 11/10 to Friday 11/14 Contractor to continue water main installation.

Looking Ahead:

East Jefferson to the Main Street intersection to remain closed for pavement operations. Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.

DIGGIN DOWNTOWN UPDATE - 6/19Date: June 19, 2026 Recent Weeks: The square is now all open to traffic! Sidewalk Installation (Fillmore St) Light Pole Installation (Fi...
Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...