Diggin Downtown Update - 11/14

Last Updated 11/24/2025Posted in DIGGIN' DOWNTOWN

Date: November 14, 2025 
Recent Weeks:
Underground Utility Service Installation (W Jefferson St)
Subgrade Compaction, Subbase and Subdrain Installation (Main St/E Jefferson St)

Next Week:
Phase 1B Main Street/East Jefferson Street Intersection.
Monday 11/17 to Friday 11/21 – Contractor to continue earthwork, compaction, subdrain installation, and paving operations.
Phase 2A Jefferson Street.
Monday 11/17 to Friday 11/21 – Contractor to work on water service installation.

Looking Ahead:
East Jefferson and the intersection of Main Street and Jefferson Street will remain closed for paving operations. Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/20Date: March 20, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...