Diggin' Downtown Update 11/26

Last Updated 12/2/2025Posted in DIGGIN' DOWNTOWN

Date: November 26, 2025

Recent Weeks:

Underground Utility Service Installation (West Jefferson St)

Subgrade Compaction, Subbase, Subdrain Installation, Paving (Main Street/East Jefferson St)

Next Week:

Phase 1B Main Street/East Jefferson Street Intersection.

Monday 12/1 to Friday 12/5 – Contractor to work on sidewalk paving operations


Phase 2A Jefferson Street.

Monday 12/1 to Friday 12/5 Contractor to continue building water service installations

 

Looking Ahead:

Main Street and the intersection of Main Street and Jefferson Street will remain closed for paving operations. West Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.

 

Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...
DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...