Recent Weeks:

Underground Utility Service Installation (West Jefferson St)

Subgrade Compaction, Subbase, Subdrain Installation, Paving (Main Street/East Jefferson St)

Next Week:

Phase 1B Main Street/East Jefferson Street Intersection.

Monday 12/1 to Friday 12/5 – Contractor to work on sidewalk paving operations


Phase 2A Jefferson Street.

Monday 12/1 to Friday 12/5 Contractor to continue building water service installations

 

Looking Ahead:

Main Street and the intersection of Main Street and Jefferson Street will remain closed for paving operations. West Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.

 

Osceola 175 – Glimpses Of The Past: Fire & Fortitude On ... A Downtown Forged by Fire Between 1874 and today, 45 major fires swept through downtown Osceola, repeatedly reshaping the square. Each b...
Osceola175- Honoring Osceola: The Warrior Behind Our Tow... 2026 marks Osceola’s 175th anniversary , and to celebrate this historic milestone, we’re launching a weekly history series highlighting ...
DIGGIN DOWNTOWN UPDATE - 1/9/26Date: January 9, 2026 Recent Weeks: Sanitary Sewer Installation (Jefferson St) Sidewalk Installation (Jefferson St) Next Week: Phase 2A ...
DIGGIN DOWNTOWN UPDATE - 12/19Date: December 19, 2025 Recent Weeks: Underground Utility Service installation (Jefferson St) Sidewalk Installation (Main St/East Jeffer...