Recent Weeks:

Underground Utility Service Installation (West Jefferson St)

Subgrade Compaction, Subbase, Subdrain Installation, Paving (Main Street/East Jefferson St)

Next Week:

Phase 1B Main Street/East Jefferson Street Intersection.

Monday 12/1 to Friday 12/5 – Contractor to work on sidewalk paving operations


Phase 2A Jefferson Street.

Monday 12/1 to Friday 12/5 Contractor to continue building water service installations

 

Looking Ahead:

Main Street and the intersection of Main Street and Jefferson Street will remain closed for paving operations. West Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.

 

DIGGIN' DOWNTOWN UPDATE - 2/27Date: February 27, 2026 Recent Weeks: Water Service Installation (Fillmore St) Paving Preparation and Installation (Jefferson St) Next W...
DIGGIN DOWNTOWN UPDATE - 2/20/26Date: February 20, 2026 Recent Weeks: Water Man Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Install...
DIGGIN DOWNTOWN UPDATE - 2/16/26Date: February 13, 2026 Recent Weeks: Water Main Installation (Fillmore St) Pavement Removal (Fillmore St) Paving Preparation and Instal...
Ribbon Cutting Celebration: Welcome Vic’s Wash HouseOn February 3, we were proud to welcome Vic’s Wash House to Osceola’s Main Street with a ribbon cutting celebration. It was a great oppo...