Diggin' Downtown Update 11/26
Date: November 26, 2025
Recent Weeks:
Underground Utility Service Installation (West Jefferson St)
Subgrade Compaction, Subbase, Subdrain Installation, Paving (Main Street/East Jefferson St)
Next Week:
Phase 1B Main Street/East Jefferson Street Intersection.
Monday 12/1 to Friday 12/5 – Contractor to work on sidewalk paving operations
Phase 2A Jefferson Street.
Monday 12/1 to Friday 12/5 – Contractor to continue building water service installations
Looking Ahead:
Main Street and the intersection of Main Street and Jefferson Street will remain closed for paving operations. West Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.