DIGGIN DOWNTOWN UPDATE - 12/5

Last Updated 12/15/2025Posted in DIGGIN' DOWNTOWN

Date: December 5, 2025  

Recent Weeks:

Underground Utility Service Installation (Jefferson St)

Paving Operations (Main St/Jefferson St)

Next Week:

Phase 1B Main Street/East Jefferson Street Intersection.

Monday 12/8 to Friday 12/12– Contractor to continue sidewalk paving operations as weather allows. Phase 2A Jefferson Street.

Monday 12/8 to Friday 12/12– Contractor to continue sanitary sewer installation.

Looking Ahead:

Main Street and the intersection of Main Street and Jefferson Street will remain closed for paving operations. Jefferson Street between Main Street and Fillmore Street will remain closed for utility installation.

DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...
DIGGIN DOWNTOWN 3/6Date: March 6, 2026 Recent Weeks: Water Service Installation (Fillmore St) Sanitary Sewer Service Installation (Fillmore St) Paving Prep...
DIGGIN' DOWNTOWN UPDATE - 2/27Date: February 27, 2026 Recent Weeks: Water Service Installation (Fillmore St) Paving Preparation and Installation (Jefferson St) Next W...