DIGGIN DOWNTOWN UPDATE - 1/9/26
Date: January 9, 2026
Recent Weeks:
Sanitary Sewer Installation (Jefferson St) Sidewalk Installation (Jefferson St)
Next Week:
Phase 2A Jefferson Street.
Monday 1/12 to Friday 1/16– Contractor to continue sanitary sewer installation and begin roadway earthwork and subdrain installation.
Looking Ahead:
Jefferson Street between Main Street and Fillmore Street will remain closed for utility and roadway installation. Fillmore Street is expected to fully close late January/early February (weather dependent).