DIGGIN DOWNTOWN UPDATE - 1/9/26

Last Updated 1/13/2026Posted in DIGGIN' DOWNTOWN

Date: January 9, 2026 
Recent Weeks:
Sanitary Sewer Installation (Jefferson St) Sidewalk Installation (Jefferson St)


Next Week:
Phase 2A Jefferson Street.
Monday 1/12 to Friday 1/16– Contractor to continue sanitary sewer installation and begin roadway earthwork and subdrain installation.
Looking Ahead: 
Jefferson Street between Main Street and Fillmore Street will remain closed for utility and roadway installation. Fillmore Street is expected to fully close late January/early February (weather dependent).
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/20Date: March 20, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...
DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...