DIGGIN DOWNTOWN UPDATE - 1/30/26

Last Updated 2/2/2026Posted in DIGGIN' DOWNTOWN

Date: January 30, 2026

Recent Weeks:
Sanitary Sewer Installation (Jefferson St)

Next Week:
Phase 2A Jefferson Street.
Monday 2/2 to Friday 2/6 – Pending warmer weather, contractor to continue sanitary and storm sewer installation. Pavement preparation along Jefferson Street will follow the completion of utility installation.

Looking Ahead:
Jefferson Street between Main Street and Fillmore Street will remain closed for utility and roadway installation. Fillmore Street is expected to fully close in late February (weather dependent).
DIGGIN DOWNTOWN UPDATE - 3/13Date: March 13, 2026 Recent Weeks: Sanitary Sewer Service Installation (Fillmore St) Storm Sewer Installation (Fillmore St) Curb and Gut...
Celebrating Community at the Greater Osceola Partnership... On Friday, March 6, the Greater Osceola Partnership Annual Dinner was held, in partnership with the Osceola Chamber Main Street and Clar...
DIGGIN DOWNTOWN 3/6Date: March 6, 2026 Recent Weeks: Water Service Installation (Fillmore St) Sanitary Sewer Service Installation (Fillmore St) Paving Prep...
DIGGIN' DOWNTOWN UPDATE - 2/27Date: February 27, 2026 Recent Weeks: Water Service Installation (Fillmore St) Paving Preparation and Installation (Jefferson St) Next W...