DIGGIN DOWNTOWN UPDATE - 2/6/26

Last Updated 2/9/2026Posted in DIGGIN' DOWNTOWN

Date: February 6, 2026

Recent Weeks:

Sanitary Sewer Installation (Jefferson St)

Pavement Removal (Fillmore St)

Next Week:

Phase 2A Jefferson Street.

Monday 2/9 to Friday 2/13 – Contractor to continue roadway and sidewalk paving.

Phase 2B Fillmore Street.

Monday 2/9 to Friday 2/13 – Contractor to begin water main installation on the east side of Fillmore Street.

Looking Ahead:

Jefferson Street between Main Street and Fillmore Street will remain closed for roadway installation.  Fillmore Street is expected to fully close February 16 (weather dependent).

DIGGIN DOWNTOWN UPDATE - 6/19Date: June 19, 2026 Recent Weeks: The square is now all open to traffic! Sidewalk Installation (Fillmore St) Light Pole Installation (Fi...
Swing By the Pocket ParkSometimes the best projects take time. What began as a simple idea nearly five years ago has grown into one of downtown Osceola's newest...
DIGGIN DOWNTOWN UPDATE - 6/12Date: June 12, 2026 Recent Weeks: Sidewalk Installation (Fillmore St) Road Paving (Fillmore St) Light Pole Installation (Fillmore St) Se...
DIGGIN DOWNTOWN UPDATE - 6/5Date: June 5, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Sidewalk Installation (Fillmore St) Road Paving (Fillmore St...