DIGGIN DOWNTOWN UPDATE - 2/16/26

Last Updated 2/16/2026Posted in DIGGIN' DOWNTOWN

Date: February 13, 2026 

Recent Weeks:
Water Main Installation (Fillmore St)
Pavement Removal (Fillmore St)
Paving Preparation and Installation (Jefferson St)

Next Week:
Phase 2A Jefferson Street.
Monday 2/16 to Friday 2/20 Contractor to continue roadway and sidewalk paving.
Phase 2B Fillmore Street.
Monday 2/16 to Friday 2/20 – Contractor to continue water main installation on the east side of Fillmore Street. All of Fillmore Street will be closing this week.

Looking Ahead:
Jefferson Street between Main Street and Fillmore Street will remain closed for roadway installation.

DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/17Date: April 17, 2026 Recent Weeks: Storm Sewer/Water Main Installation (Fillmore St) Sidewalk Installation (Fillmore St) Next Week: Phas...
DIGGIN DOWNTOWN UPDATE - 4/3Date: April 3, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Pavement Removal (Fillmore St) Permeable Paver Installation (Je...
DIGGIN DOWNTOWN UPDATE - 3/30Date: March 27, 2026 Recent Weeks: Storm Sewer Installation (Fillmore St) Curb and Gutter Installation (Jefferson St) Permeable Paver In...