DIGGIN' DOWNTOWN UPDATE - 2/27
Date: February 27, 2026
Recent Weeks:
Water Service Installation (Fillmore St)
Paving Preparation and Installation (Jefferson St)
Next Week:
Phase 2A Jefferson Street.
Monday 3/2 to Friday 3/6 – Contractor to continue permeable paver installation, sidewalk paving, and curb and gutter installation.
Phase 2B Fillmore Street.
Monday 3/2 to Friday 3/6 – Contractor to complete water service installation and begin working on sanitary service installations.
Looking Ahead:
Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.