DIGGIN DOWNTOWN UPDATE - 3/13
Date: March 13, 2026
Recent Weeks:
Sanitary Sewer Service Installation (Fillmore St)
Storm Sewer Installation (Fillmore St)
Curb and Gutter Installation (Jefferson St)
Permeable Paver Installation (Jefferson St)
Sidewalk Installation (Jefferson St)
Next Week:
Phase 2A Jefferson Street.
Monday 3/16 to Friday 3/20 – Curb and gutter, permeable pavers, permeable paver aggregate, and sidewalk installation.
Phase 2B Fillmore Street.
Monday 3/16 to Friday 3/20 –Continue storm sewer installation.
Looking Ahead:
Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.