DIGGIN DOWNTOWN UPDATE - 3/13

Last Updated 3/13/2026Posted in DIGGIN' DOWNTOWN

Date: March 13, 2026

Recent Weeks:

Sanitary Sewer Service Installation (Fillmore St)

Storm Sewer Installation (Fillmore St)

Curb and Gutter Installation (Jefferson St)

Permeable Paver Installation (Jefferson St)

Sidewalk Installation (Jefferson St)


Next Week:

Phase 2A Jefferson Street.

Monday 3/16 to Friday 3/20 – Curb and gutter, permeable pavers, permeable paver aggregate, and sidewalk installation.

Phase 2B Fillmore Street.

Monday 3/16 to Friday 3/20 –Continue storm sewer installation.


 

Looking Ahead:

Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.


DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...
DIGGIN DOWNTOWN UPDATE - 5/16Date: May 22, 2026 Recent Weeks: Permeable Paver Rock Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Next Week: P...
DIGGIN DOWNTOWN UPDATE - 5/15Date: May 15, 2026 Recent Weeks: Permeable Paver Rock Installation (Fillmore St) Subdrain Installation Paving (Fillmore St) Curb and Gut...
Osceola Recognized at 2026 Main Street Iowa Development ... Osceola received statewide recognition at the 2026 Main Street Iowa Development Awards, held May 8 in West Des Moines as Main Street Iow...