DIGGIN DOWNTOWN UPDATE - 3/20
Date: March 20, 2026
Recent Weeks:
Storm Sewer Installation (Fillmore St)
Curb and Gutter Installation (Jefferson St)
Permeable Paver Installation (Jefferson St)
Sidewalk Installation (Jefferson St)
Next Week:
Phase 2A Jefferson Street.
Monday 3/23 to Friday 3/27 –
· Install permeable pavers south side of Jefferson Street
· Install pocket park aggregate and permeable paver system
· Install remaining sections of PCC curb and gutter and sidewalk.
Phase 2B Fillmore Street.
Monday 3/16 to Friday 3/20 –Continue storm sewer installation.
Looking Ahead:
Jefferson Street and Fillmore Street will remain closed for roadway/utility installation.