DIGGIN DOWNTOWN UPDATE - 4/24

Last Updated 4/27/2026Posted in DIGGIN' DOWNTOWN

 Date: April 24, 2026

Recent Weeks:

Sanitary Sewer/Water Main Installation (Fillmore St)

Paving Preparation (Fillmore St)

Next Week:

Phase 2A Jefferson Street.

Monday 4/27 to Friday 5/1:

·         Install light poles

 

Phase 2B Fillmore Street.

Monday 4/27 to Friday 5/1:

·         Continue roadway paving

·         Continue utility installation in Fillmore/Jefferson intersection

·         Install electrical conduit

 

Looking Ahead:

Fillmore Street and the western section of Jefferson Street will remain closed for roadway/utility installation.

 

DIGGIN DOWNTOWN UPDATE - 5/29Date: May 29, 2026 Recent Weeks: Permeable Paver Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Paving Preparatio...
DIGGIN DOWNTOWN UPDATE - 5/16Date: May 22, 2026 Recent Weeks: Permeable Paver Rock Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Next Week: P...
DIGGIN DOWNTOWN UPDATE - 5/15Date: May 15, 2026 Recent Weeks: Permeable Paver Rock Installation (Fillmore St) Subdrain Installation Paving (Fillmore St) Curb and Gut...
Osceola Recognized at 2026 Main Street Iowa Development ... Osceola received statewide recognition at the 2026 Main Street Iowa Development Awards, held May 8 in West Des Moines as Main Street Iow...