DIGGIN DOWNTOWN UPDATE - 5/1
Date: May 1, 2026
Recent Weeks:
Sanitary Sewer/Water Main Installation (Fillmore St)
Mainline Paving (Fillmore St)
Next Week:
Phase 2B Fillmore Street.
Monday 5/4 to Friday 5/8:
· Continue roadway paving
· Begin Excavation in permeable paver locations.
· Continue utility installation in Fillmore/Jefferson intersection
Looking Ahead:
Fillmore Street and the western section of Jefferson Street will remain closed for roadway/utility installation.