DIGGIN DOWNTOWN UPDATE - 5/8

Last Updated 5/26/2026Posted in DIGGIN' DOWNTOWN

Date: May 8, 2026 

Recent Weeks:
Storm Sewer Installation (Fillmore St)
Mainline Paving (Fillmore St)
Permeable Paver Installation (Fillmore St)

Next Week:
Phase 2B Fillmore Street.
Monday 5/11 to Friday 5/15:
• Continue excavation and rock installation in permeable paver locations.
• Continue subdrain and curb and gutter installation.
• Continue utility installation in Fillmore/Jefferson intersection.

Looking Ahead:
Fillmore Street and the western section of Jefferson Street will remain closed for roadway/utility installation.
DIGGIN DOWNTOWN UPDATE - 5/16Date: May 22, 2026 Recent Weeks: Permeable Paver Rock Installation (Fillmore St) Curb and Gutter Installation (Fillmore St) Next Week: P...
DIGGIN DOWNTOWN UPDATE - 5/15Date: May 15, 2026 Recent Weeks: Permeable Paver Rock Installation (Fillmore St) Subdrain Installation Paving (Fillmore St) Curb and Gut...
DIGGIN DOWNTOWN UPDATE - 5/1Date: May 1, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Mainline Paving (Fillmore St) Next Week: Phase 2B F...
DIGGIN DOWNTOWN UPDATE - 4/24Date: April 24, 2026 Recent Weeks: Sanitary Sewer/Water Main Installation (Fillmore St) Paving Preparation (Fillmore St) Next Week: Phas...