DIGGIN DOWNTOWN UPDATE - 5/15
Date: May 15, 2026
Recent Weeks:
Permeable Paver Rock Installation (Fillmore St)
Subdrain Installation Paving (Fillmore St)
Curb and Gutter Installation (Fillmore St)
All storm, sewer and water utility work has been completed.
Next Week:
Phase 2B Fillmore Street.
Monday 5/18 to Friday 5/22:
Curb and gutter installation on west side.
Sidewalk installation on east side.
Light pole base installation.
Begin concrete preparation in Fillmore/Jefferson intersection.
Looking Ahead:
Fillmore Street and the western section of Jefferson Street will remain closed for roadway installation.