DIGGIN DOWNTOWN UPDATE - 5/16
Date: May 22, 2026
Recent Weeks:
Permeable Paver Rock Installation (Fillmore St)
Curb and Gutter Installation (Fillmore St)
Next Week:
Phase 2B Fillmore Street.
Tuesday 5/26 to Friday 5/29:
Continue permeable paver installation.
Continue light pole base and conduit installation.
Begin concrete preparation in Fillmore/Jefferson intersection.
*There is no work anticipated on Monday the 25th (Memorial Day)
Looking Ahead:
Fillmore Street and the western section of Jefferson Street will remain closed for roadway installation.