DIGGIN DOWNTOWN UPDATE - 5/29
Date: May 29, 2026
Recent Weeks:
Permeable Paver Installation (Fillmore St)
Curb and Gutter Installation (Fillmore St)
Paving Preparation (Fillmore St/Jefferson St)
Conduit and Light Pole Base Installation (East side Fillmore St)
Next Week:
Phase 2B Fillmore Street.
Tuesday 6/1 to Friday 6/5:
·Continue light pole base and conduit installation (West side Fillmore St).
·Begin concrete paving in Fillmore/Jefferson intersection and along Fillmore south of the intersection.
Looking Ahead:
Fillmore Street and the western section of Jefferson Street will remain closed for roadway installation.