DIGGIN DOWNTOWN UPDATE - 6/12
Date: June 12, 2026
Recent Weeks:
Sidewalk Installation (Fillmore St)
Road Paving (Fillmore St)
Light Pole Installation (Fillmore St)
Seeding/Restoration (Fillmore St)
Next Week:
Phase 2B Fillmore Street.
Monday 6/15 to Friday 6/19:
· Finish sidewalk installation at Fillmore/Jefferson intersection
· Joint Sealing along Fillmore Street
· Site Cleanup and Restoration
Looking Ahead:
Fillmore Street and the western section of Jefferson Street will remain closed for roadway installation.


.jpg)