DIGGIN' DOWNTOWN UPDATE - 2/21Recent Weeks: -No work week (2/17) due to low temperatures -Water Main Installation Next Week: Phase 1A Washington Street Monday 2/24 : ...
DIGGIN' DOWNTOWN UPDATE - 2/7Recent Weeks: · Water Main Installation · Light poles to be removed · Connect new water line to both hydrants Next Week: · Mon-Wed testi...
Downtown Streetscape Water Main Work Begins January 14thOsceola’s historic downtown square streetscape project has been underway for less than a month. Partial lane closures along the north si...
DIGGIN' DOWNTOWN UPDATE - 1/3Recent Weeks: · General site set up and safety fence installation · Pavement removal · Existing utility investigation Next Week: Phase 1...
Downtown Streetscape Construction Project Beginning MondayDate : December 13, 2024 Next Week: Phase 1A Washington Street Monday 12/16 – Washington Street will be closed for construction from the...