DIGGIN' DOWNTOWN UPDATE - 7/18Date: July 18, 2025 Recent Weeks: (Washington Street/Main Street) Storm Sewer installation Permeable Paver Installation (Washington St) ...
DIGGIN' DOWNTOWN UPDATE - 7/11Date: July 11, 2025 Recent Weeks: Roadway Extended East to Intersection (Washington St) Permeable Paver Installation (Washington St) Wes...
DIGGIN' DOWNTOWN UPDATE - 7/3Recent Weeks: Concrete Paving Operations (Washington St) Permeable Paver Installation (Washington St) Storm Sewer installation (Washingt...
DIGGIN' DOWNTOWN UPDATE - 6/27Date: June 27, 2025 Recent Weeks: Concrete Paving Operations (Washington St) Permeable Paver Installation (Washington St) Storm Sewer in...
DIGGIN' DOWNTOWN UPDATE - 6/20Date: June 20, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Permeable Paver Insta...
DIGGIN DOWNTOWN UPDATE - 6/13Date: June 13, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Storm Sewer Installat...
DIGGIN' DOWNTOWN UPDATE - 6/6Date: June 6, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Storm Sewer installati...
DIGGIN' DOWNTOWN UPDATE - 5/30Date: May 30, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Next Week: Phase 1A Wa...
DIGGIN' DOWNTOWN UPDATE - 5/23Date: May 23, 2025 Recent Weeks: Subdrain Installation (Washington St) Concrete Paving Operations (Washington St) Pavement Removals (Mai...
DIGGIN' DOWNTOWN UPDATE - 5/16Date: May 16, 2025 Recent Weeks: Storm Sewer Installation (Washington St) Concrete Paving Operations (Washington St) Pavement Removals (...
DIGGIN' DOWNTOWN UPDATE - 5/12Date: May 9, 2025 Recent Weeks: Storm Sewer Installation Subgrade Preparation Next Week: Phase 1A Washington Street Monday 5/12 to Frida...
DIGGIN' DOWNTOWN UPDATE - 5/2Date: May 2, 2025 Recent Weeks: Storm Sewer Installation Next Week: Phase 1A Washington Street Monday 5/5 to Tuesday 5/6 – Contractor to...