Diggin Downtown Update 11/21Date: November 21, 2025 Recent Weeks: Underground Utility Service Installation (Jefferson St) Subgrade Compaction, Subbase, Subdrain Ins...
Diggin Downtown Update - 11/14Date: November 14, 2025 Recent Weeks: Underground Utility Service Installation (W Jefferson St) Subgrade Compaction, Subbase and Subdrai...
DIGGIN DOWNTOWN UPDATE - 10/31Date: October 31, 2025 Recent Weeks: Underground Utility Service Installation (Main St/E Jefferson St) Permeable Paver Installation (Mai...
DIGGIN DOWNTOWN UPDATE - 10/24Date: October 24, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Curb and Gutter installation (Main ...
Diggin Downtown Update - 10/17Date: October 17, 2025 Recent Weeks: Underground Utility Service installation (Main St/Jefferson St) Curb and Gutter installation (Main ...
Diggin Downtown Update - 10/10Date: October 10, 2025 Recent Weeks: Underground Utility Service Installation (East Jefferson St) Lighting System Installation (Washingt...
Diggin' Downtown Update - 10/3Date: October 3, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Lighting System Installation (Washin...
DIGGIN' DOWNTOWN UPDATE - 9/26Date: September 26, 2025 Recent Weeks: Underground Utility Service Installation (Main St/Jefferson St) Water Main Installation (E Jeffer...
DIGGIN DOWNTOWN UPDATE - 9/12Date: September 12, 2025 Recent Weeks: Underground Utility Service (Main St) Paving Operations (E Washington St, Washington & Main Stree...
DIGGIN DOWNTOWN UPDATE - 9/8Date: September 5, 2025 Recent Weeks: Underground Utility Service Installation (Main St) Paving Operations (East Washington St) Pavement...
DIGGIN DOWNTOWN UPDATE - 8/29Date: August 29, 2025 Recent Weeks: Underground Utility Service Installation (Main St) Paving Operations (East Washington St) Fillmore a...