DIGGIN' DOWNTOWN UPDATE - 4/25Date: April 25, 2025 Recent Weeks: Storm Sewer Installation Next Week: Phase 1A Washington Street Monday 4/28 to Friday 5/2 – Contractor...
DIGGIN' DOWNTOWN UPDATE - 4/18Date: April 18, 2025 Recent Weeks: Storm Sewer Installation Sidewalk Installation ADA Accessible Ramps Poured Next Week: Phase 1A Washin...
DIGGIN' DOWNTOWN UPDATE - 4/11Date: April 11, 2025 This Past Week: Storm Sewer Installation Sidewalk Installation Next Week: Phase 1A Washington Street Monday 4/14 to...
DIGGIN' DOWNTOWN UPDATE - 4/4Date: April 4, 2025 Recent Weeks: Sanitary Sewer Installation Manhole Installation Pavement Removal Next Week: Phase 1A Washington Stree...
DIGGIN' DOWNTOWN UPDATE - 3-28Recent Weeks: - Water main installation and water main services completed on Washington Street. -Sanitary sewer service installation Nex...
DIGGIN' DOWNTOWN UPDATE - 3/21Recent Weeks: Water main and service installation. Light poles on Washington Street Removed. Washington Street watermain connected to Ma...
DIGGIN' DOWNTOWN UPDATE - 3/7Date: March 7, 2025 Recent Weeks: Water Main Installation Pavement Removal Next Week: Phase 1A Washington Street Monday 3/10 – Contracto...
DIGGIN' DOWNTOWN UPDATE - 2/21Recent Weeks: -No work week (2/17) due to low temperatures -Water Main Installation Next Week: Phase 1A Washington Street Monday 2/24 : ...
DIGGIN' DOWNTOWN UPDATE - 2/7Recent Weeks: · Water Main Installation · Light poles to be removed · Connect new water line to both hydrants Next Week: · Mon-Wed testi...
DIGGIN' DOWNTOWN UPDATE - 1/3Recent Weeks: · General site set up and safety fence installation · Pavement removal · Existing utility investigation Next Week: Phase 1...